by hadimarashy | Sep 25, 2020 | Case Studies, Industrial
Client : BAA Gatwick / Taylor Woodrow Programme : 18 weeks Value : £250,000 Download Case Study Overview Existing Structure & Location: Hangar 5 & PL7 Buildings were industrial buildings, originally constructed to provide an aircraft hangar, maintenance...
by hadimarashy | Sep 24, 2020 | Case Studies, Industrial
Client : Plutus EstatesProgramme : 32 weeksValue : £1.5m Download Case StudyLOCATION & OVERVIEW The project consisted of 33 acres split over 2 sites. The North site contained the former 1920’s Shredded Wheat Factory of which the original factory and silos were...
by hadimarashy | Sep 23, 2020 | Case Studies, Industrial
Client : J F FinneganProgramme : 11 weeksValue : £230k Download Case Study OVERVIEW The overall scheme at Block 90, Alderley Park was to soft strip and carry out the internal demolition of an existing 5 storey office block, in order to facilitate a full height...
by hadimarashy | Sep 22, 2020 | Case Studies, Concrete Cutting Case Studies
Client : Primark / Scudder Demolition Programme : 10 months Value : £300k Download Case Study OVERVIEW One of Birmingham’s premiere shopping destinations closed in 2016 after trading for 29 years. The centre was being be converted into a four storey Primark store...
by hadimarashy | Sep 21, 2020 | Case Studies, Concrete Cutting Case Studies
Client : Thames Tideway Tunnel / CVB Joint Venture Programme : 6 months Value : £350k Download Case Study OVERVIEW John F Hunt Concrete Cutting were involved in the entire Thames Tideway Sewer project, working on the tunnels to the East, West and the adjoining Central...
by hadimarashy | Sep 20, 2020 | Case Studies, Concrete Cutting Case Studies
Client : Thames Tideway Tunnel / FLO (Ferrovial Laing O’Rourke) JV Programme : 5 months Value : £140k Download Case Study OVERVIEW The Ferrovial Agroman and Laing O’Rourke joint venture involved building the central section of the Thames Tideway...