Let’s all
INDUCTION PROCESS TO PROJECTS get home safely,
every day
SEAT ALL COLLECT CSCS AND TASK COMPLETED ALL OPERATIVES RAMS BRIEFINGS
OPERATIVES IN SPECIFIC QUALIFICATION SITE SAFETY RETURN TO RAMS briefingscarried out by
INDUCTION CARDS (WORKING AT HEIGHT, PROFORMA INDUCTION Operative’s Foreman, followed
ROOM IPAF PASMA, SLINGERS) ROOM AND by appropriate PPE and
Ensure copy attached to induction AWAIT THEIR Permits Issued.
form and any qualifications entered SECTION
onto training matrix. ‘White’ CSCS SUPERVISORS
Cards not to be accepted, Health Carried out by: Designated
and Safety test Pass Certs alone, also individual (Project Manager,
unacceptable. Construction Manager,
Carried out by: Carried out by: Demolition Manager, Section
Office Manager. Carried out by: Office Manager Office Manager Supervisor).
OPENING SPEECH BY PLAY INDUCTION VIDEO LOG OPERATIVES ONTO SECTION
PROJECT MANAGER AND OR POWERPOINT DONSEED SUPERVISORS TAKE
STATING THE SAFETY PRESENTATION OPERATIVES ONTO
COMMITMENT ON A SITE
ONE TO ONE LEVEL. Basic safety orientation and
site rules can be delivered
by office manager or similar
Carried out by: Carried out by: Carried out by:
Project Manager Site Management Team Office Manager
See attached safety or designated person
commitment document on
next page
The above procedure must be followed for all new starts to projects