                              FLOOR BY FLOOR WORKS AND DEMOLITION                                                 get home safely,
                              EDGE PROTECTION.                                                                    every day





   1                                                   2       Demolition area to be excluded at           Types of edge protection to be
                                                               all times.                                  used for demolition works.



                                                                                                                                SG4a edge
                                                                                                                                protection system.






                                                                       Scaffold to be sequentially struck as
                                                                       works progress with 2m above area
                                                                       remaining.
        Best practice is to carry out demolition from the floor below, working on
        a floor by floor sequence. This allows for the level works are being
        carried out on to be excluded and removes the need for operatives to
        access the slab under demolition reducing the risk of works at height
        and the risk of falling materials and debris.
   3                                                   4
              No requirement to access level
              with live edge.





                                                                                                                                 Pedestrian
                                                                                                                                 barriers are not
                                                                                                                                 to be used as
                                                                                                                                 edge
                                                                                                                                 protection, only
                                                                                                                                 for demarking
                                                                                                                                 access routes
                                                                                                                                 and areas.
                   Props recycled to lower levels as        Access to all areas of risk are to be
                   per TW design as works                   excluded via physical barriers
                   proceeded