Page 70 - Visual Guidance Handbook
P. 70
Let’s all
CLIMBING SCREEN SYSTEMS get home safely,
every day
Safe Screen System is a hydraulic The system is to cover 4 x levels (1) wet
climbing system. This is to be installed on deck / live deck. (2) level with falsework
structures where the risk assessment 1 in place. (3) back propped level (4)
deems that there is a significant risk of struck level.
falling materials or equipment. Typically
this will be used on high rise structures 2 The system provides floor to soffit edge
(structures exceeding 10 floors or where protection and can be used to fully
there is a proximity risk (e.g structure is enclose the structure or partially cover
close to site perimeter or sensitive 3 high risk elevations.
structures such as rail assets.
System will be installed and operated by
4 trained and competent operatives with
training provided by the system provider.
2 x integrated staircase’s are to be
incorporated within the screen.
This will remove the need for ladder
access between platforms and
allow for structural stairs to be
Top platform to align excluded whilst under construction
with falsework on the upper 4 x levels.
construction
removing the need Stairs locations are to be planned
for cantilever sections to accommodate pour layout and
of falsework. maintain access to both the area
being poured and any area under
Hinged trapdoors construction. Falsework will
provide seal with commence at a stairs location
poured decks (these allowing for the stairs to be utilised
must remain closed to access the deck under
at all times with the construction eliminating the need
exception of when for a ladder access to this.
the screen is climbed.
Anchors installed as per TW
design and pre jump Page 70
inspection / permit to be
completed prior to all lifting
operations